Concrete Calculator — Cubic Yards, Bags and Cost

Calculate concrete for slabs, footings, columns, stairs and post holes. Get cubic yards, 40/60/80 lb bag counts, weight and an estimated cost instantly.

%

Covers spillage, uneven subgrade and over-excavation.

$
—
Enter your dimensions to see cubic yards, bag counts and cost.
ad-slot

Concrete Bag and Yardage Reference

Cubic yards and 80 lb bags by slab area and thickness — tap any cell to calculate

Slab area4 in thick5 in thick6 in thick
50 sq ft
100 sq ft
150 sq ft
200 sq ft
300 sq ft
400 sq ft
500 sq ft

Slab Thickness by Use

ThicknessTypical useNotes
4 inPatios, walkways, sheds and driveways used by carsWire mesh or no reinforcement is common. Compact 4 in of gravel sub-base and add control joints every 8 to 10 ft.
5 inDriveways with occasional light trucksUse #3 rebar or mesh on chairs near mid-depth over a compacted 4 to 6 in gravel base.
6 inGarage floors, RV pads and regular heavy vehiclesUse #3 or #4 rebar on a 16 to 24 in grid over a well-compacted 6 in gravel base.
8 inCommercial slabs and heavy equipmentUsually engineered. Expect #4 rebar in a tighter grid, a compacted engineered base and a design strength of 4,000 psi or more.

How to calculate concrete

Concrete is sold by volume, and in the United States the unit is the cubic yard. The core formula for any rectangular pour is length × width × thickness, with every dimension in feet, which gives cubic feet. Divide by 27 to convert to cubic yards, because a cubic yard is 3 ft × 3 ft × 3 ft = 27 cubic feet. The only common trap is thickness: slabs are described in inches, so divide inches by 12 before multiplying. Filling the hollow cores of a block wall is ordered the same way, by volume, and the block wall calculator works out the cubic yards of core fill for you.

Here is a full worked example. A patio measures 10 ft × 12 ft and is poured 4 in thick. Four inches is 4 ÷ 12 = 0.333 ft, so the volume is 10 × 12 × 0.333 = 40 cubic feet. Dividing by 27 gives 40 ÷ 27 = 1.48 cubic yards. Footings use the same box maths with depth in place of thickness, and if you have several footings, rebar or a frost depth to meet, the dedicated footing calculator handles them together. Columns and post holes are cylinders, so use π × radius² × height, and for a post set in concrete subtract the volume the post displaces. If you are pouring into round form tubes, the form tube calculator also works out how many tubes to buy and how to cut them. Stairs are the sum of each step's block, which is width × run × rise × (steps × (steps + 1) ÷ 2) for solid steps, plus any platform.

If you are mixing from bags, divide your cubic feet by the yield printed on the bag. An 80 lb bag yields about 0.60 cubic feet, which means 45 bags per cubic yard. A 60 lb bag yields 0.45 cubic feet (60 bags per yard) and a 40 lb bag yields 0.30 cubic feet (90 bags per yard). Always round up to a whole bag, since a part bag cannot be bought. For the 40 cubic foot patio above, that is 40 ÷ 0.60 = 66.7, so 67 bags of 80 lb. Fresh concrete weighs about 150 lb per cubic foot, so the same patio is roughly 6,000 lb, or 3 tons, before you add the sub-base. If you need the load or haulage side of that number, such as what a floor can carry or how many trips a trailer needs, the concrete weight and load check covers it.

The break-even between bags and ready-mix is roughly 1 cubic yard. Below that, bagged concrete is convenient and avoids the delivery and short-load fees that suppliers commonly charge on small orders. Above it, mixing by hand stops making sense: one yard is 45 bags of 80 lb, and each bag weighs 80 lb, so you would be lifting, mixing and placing about 3,600 lb of material before it starts to set. Ready-mix arrives ready to place, is usually cheaper per yard at that scale, and gives a more consistent mix, which matters for strength and for avoiding cold joints in a large pour.

Finally, plan for waste. Real pours always use more concrete than the drawing suggests, because forms bow slightly, the subgrade is never perfectly level, some material is spilled, and the bottom of the truck chute or wheelbarrow never empties completely. A 10% allowance is the usual default: it is large enough to absorb these small losses, yet small enough not to leave a large pile of leftover concrete. Use 5% for a tidy pour into precise forms and 15% or more for rough excavation, stepped footings or hard-to-reach sites. Running short mid-pour creates a cold joint that weakens the slab, and a second delivery usually triggers another minimum charge, so it is almost always cheaper to over-order slightly.

How to use this calculator

  1. 01Pick the shape you are pouring: slab, footing, column, stairs or post hole.
  2. 02Enter each dimension and choose its unit. Feet, inches, yards, metres and centimetres can be mixed.
  3. 03Adjust the waste allowance and the price per cubic yard to match your job and your supplier.
  4. 04Read cubic yards, bag counts, weight and the estimated cost, which update as you type.
  5. 05Use the reference table to jump to a common slab size, then confirm your order with your supplier.

Common questions

How much concrete do I need for a 10x10 slab?
A 10 ft × 10 ft slab poured 4 in thick needs 33.3 cubic feet, which is 1.23 cubic yards. At 6 in thick it needs 50 cubic feet, or 1.85 cubic yards. Add about 10% on top of either figure to cover spillage and an uneven subgrade, so order roughly 1.36 cubic yards for the 4 in slab.
How many 80 lb bags of concrete are in a cubic yard?
One cubic yard is 27 cubic feet, and an 80 lb bag yields about 0.60 cubic feet, so you need 45 bags per cubic yard. A 60 lb bag yields 0.45 cubic feet (60 bags per yard) and a 40 lb bag yields 0.30 cubic feet (90 bags per yard). Always round up to a whole bag.
How do I calculate concrete in cubic yards?
Multiply length × width × thickness in feet to get cubic feet, then divide by 27. Convert inches to feet first by dividing by 12. For a 10 ft × 12 ft slab at 4 in thick, that is 10 × 12 × 0.333 = 40 cubic feet, or 1.48 cubic yards.
How thick should a concrete slab be?
4 in is the standard for patios, walkways, sheds and driveways used by cars. Use 5 in for driveways that see occasional light trucks, 6 in for garage floors, RV pads and regular heavy vehicles, and 8 in for commercial slabs and heavy equipment. Thicker slabs are usually paired with rebar or wire mesh on a compacted gravel base.
Is it cheaper to mix my own concrete or order ready-mix?
For small jobs under about 1 cubic yard, bagged concrete is usually easier and avoids delivery or short-load fees. Above roughly 1 cubic yard, ready-mix is normally cheaper per yard and far less work, because 45 or more 80 lb bags must be mixed and placed before the concrete starts to set. Bagged concrete typically works out to $225 to $360 per cubic yard.
How much does a cubic yard of concrete cost?
Ready-mix concrete commonly costs $130 to $180 per cubic yard in the US, and this calculator defaults to $140. Delivery fees, short-load charges for small orders, color or fiber additives and regional prices can raise the final bill. Treat the result as an estimate and confirm a quote with your supplier.
How much does a cubic yard of concrete weigh?
Standard concrete weighs about 150 lb per cubic foot, so one cubic yard (27 cubic feet) weighs about 4,050 lb, or roughly 2 tons. A 4 in, 10 ft × 12 ft slab at 40 cubic feet weighs about 6,000 lb. Check that your vehicle, wheelbarrows and forms can handle the load.
How much extra concrete should I order for waste?
Order 5% to 10% extra for most jobs, and use 10% as the safe default. Spillage, an uneven or over-excavated subgrade and slightly bowed forms all consume more concrete than the plan on paper. Go up to 15% for rough ground or complex shapes, because running short mid-pour is far more costly than having a little left over.
What is the difference between a slab and a footing?
A slab is a wide, flat pour that sits on the ground, such as a patio, garage floor or shed base, and is typically 4 to 6 in thick. A footing is a narrower, deeper pour in a trench that spreads the load of a wall, deck post or foundation down to firm soil, and is often 8 to 12 in or more deep. Both are measured as length × width × thickness or depth.
How long does concrete take to cure before I can use it?
Concrete is usually firm enough to walk on after 24 to 48 hours and can take light vehicle traffic after about 7 days. It reaches its design strength at 28 days, so keep heavy loads off until then. Keep the surface damp or covered for the first week, since drying out too fast causes cracking and weaker concrete.
ad-slot
Related calculators

Results are estimates, not quotes. The cost figure uses a user-editable national-average ready-mix price and excludes labour, forms, reinforcement and delivery minimums. Confirm quantities with your supplier before ordering. For a full slab price including labour, use the Concrete Slab Cost Calculator. Last updated: October 1, 2026.