Concrete Mix Ratio Calculator — Cement, Sand, Gravel
Work out cement, sand, aggregate and water for any mix ratio or strength grade. Imperial and metric, with bag counts, cost and a per-batch recipe.
M15 / C12/15 · about 2,200 psi. General slabs, paths, patios, footings.
Work out the volume from a slab
Material prices
Concrete Mix Ratios and What They Are For
Nominal mixes by volume. Bags are 94 lb for one cubic yard at the default water-cement ratio. Tap Use to load a row.
| Ratio | Grade | Strength | Water-cement | Bags per yd³ | Typical use | |
|---|---|---|---|---|---|---|
| 1:4:8 | M7.5 / Below C8/10 | 1,100 psi · 7.6 MPa | 0.70 | 3.2 | Mass fill, blinding, non-structural bedding | Use |
| 1:3:6 | M10 / C8/10 | 1,500 psi · 10.3 MPa | 0.60 | 4.2 | Foundations on firm soil, mass concrete, floor base | Use |
| 1:2:4 | M15 / C12/15 | 2,200 psi · 15.2 MPa | 0.50 | 5.9 | General slabs, paths, patios, footings | Use |
| 1:2:3 | M20 / C16/20 | 2,900 psi · 20.0 MPa | 0.50 | 6.9 | Driveways, garage floors, steps | Use |
| 1:1.5:3 | M20 / C16/20 | 2,900 psi · 20.0 MPa | 0.45 | 7.6 | Reinforced slabs, beams, lintels | Use |
| 1:1.5:2.5 | M25 / C20/25 | 3,600 psi · 24.8 MPa | 0.45 | 8.3 | Columns, heavy-duty slabs, water-retaining work | Use |
| 1:1:2 | M30 / C25/30 | 4,400 psi · 30.3 MPa | 0.40 | 10.4 | Posts, precast, high-strength structural parts | Use |
Strength Grades: M, C and psi
Indian M grades are cube strengths. European C grades are written cylinder/cube, so C20/25 sits near M25.
| Grade | European | MPa | psi | Nearest ratio |
|---|---|---|---|---|
| M7.5 | Below C8/10 | 7.5 | 1,100 | 1:4:8 |
| M10 | C8/10 | 10 | 1,500 | 1:3:6 |
| M15 | C12/15 | 15 | 2,200 | 1:2:4 |
| M20 | C16/20 | 20 | 2,900 | 1:1.5:3 |
| M25 | C20/25 | 25 | 3,600 | 1:1.5:2.5 |
| M30 | C25/30 | 30 | 4,400 | 1:1:2 |
| M35 | C28/35 | 35 | 5,100 | Designed mix needed |
| M40 | C32/40 | 40 | 5,800 | Designed mix needed |
Materials per Cubic Yard and per Cubic Metre
Dry materials for one unit of wet concrete at each mix's default water-cement ratio, no waste allowance.
| Ratio | Cement | Sand | Aggregate | Water |
|---|---|---|---|---|
| 1:2:4 | 5.94 ft³ · 558 lb · 5.9 bags 0.220 m³ · 317 kg · 6.3 bags | 11.9 ft³ · 1,188 lb 0.440 m³ · 705 kg | 23.8 ft³ · 2,257 lb 0.880 m³ · 1,339 kg | 33.5 gal per yd³ 158 L per m³ |
| 1:3:6 | 4.16 ft³ · 391 lb · 4.2 bags 0.154 m³ · 222 kg · 4.4 bags | 12.5 ft³ · 1,247 lb 0.462 m³ · 740 kg | 24.9 ft³ · 2,370 lb 0.924 m³ · 1,406 kg | 28.1 gal per yd³ 133 L per m³ |
| 1:2:3 | 6.93 ft³ · 651 lb · 6.9 bags 0.257 m³ · 370 kg · 7.4 bags | 13.9 ft³ · 1,386 lb 0.513 m³ · 822 kg | 20.8 ft³ · 1,975 lb 0.770 m³ · 1,172 kg | 39.1 gal per yd³ 185 L per m³ |
| 1:1.5:3 | 7.56 ft³ · 711 lb · 7.6 bags 0.280 m³ · 403 kg · 8.1 bags | 11.3 ft³ · 1,134 lb 0.420 m³ · 673 kg | 22.7 ft³ · 2,155 lb 0.840 m³ · 1,278 kg | 38.3 gal per yd³ 181 L per m³ |
How concrete mix ratios work
A concrete mix ratio lists the volumes of cement, sand and coarse aggregate in that order, so 1:2:4 is one part cement, two parts sand and four parts gravel. The parts are by volume, which is why a bucket works as the measuring unit on a small job. This mix design calculator also works from a strength grade, because the grade is what a job actually specifies and the ratio is only a way of reaching it. M20 means 20 MPa, about 2,900 psi, on a 28-day cube, and C16/20 is the European grade that sits closest to it.
Dry materials take up more room than the concrete they make. Loose sand and gravel are full of air gaps, and once cement paste and water fill them the pile shrinks, so you need about 1.54 times the wet volume in dry material. A cubic yard of concrete is 27 cubic feet, so you load 41.6 cubic feet of dry cement, sand and gravel. At 1:2:4 the seven parts split that into 5.94 cubic feet of cement, 11.88 of sand and 23.76 of aggregate. Cement at 94 lb per cubic foot comes to 558 lb, which is six bags. To size the pour in the first place, use a concrete volume calculator and enter the result here.
Strength depends on water as much as on the ratio. Cement needs only about a quarter of its weight in water to hydrate, and the rest exists to make the mix workable. Surplus water leaves tiny voids as it evaporates, so each 0.1 added to the water-cement ratio costs roughly 13% of strength in this calculator's estimate. At 0.50 a 94 lb bag takes 47 lb of water, about 5.6 gallons. Damp sand already holds water, so hold back part of the allowance and add the rest until the mix just slumps. The strength figure is an Abrams-style rule of thumb for comparing mixes and is not a test result.
Choosing a ratio for the job
Pick the leanest mix that meets the strength you need, because every extra bag of cement adds cost and shrinkage. Mass fill, blinding and bedding need little more than 1:4:8. Footings on firm soil and floor bases are comfortable at 1:3:6 or 1:2:4. Slabs, paths and patios usually land at 1:2:4, and driveways, garage floors and steps do better at 1:2:3 or 1:1.5:3, where the extra cement resists wear and freeze-thaw. Posts, precast parts and anything heavily loaded move up to 1:1:2.
Nominal ratios stop being reliable above M30. A strength of M35 or M40 depends on the grading and cleanliness of your sand and aggregate, and it needs a designed mix with test cubes. The same applies to any structural member, such as a beam, column or suspended slab, where an engineer must specify the mix. For ordinary sand gravel cement work on the ground, the table ratios are a sound starting point.
Mixing by hand, by drum, or buying premix
Batch size is set by your mixer. The recipe above converts the totals into whole buckets for one drum, so every batch carries the same proportions. Treat the drum rating as the wet concrete it turns out, and fill to about two thirds if your mixer is rated for dry loading. Add about three quarters of the water first, then the aggregate, cement and sand, and bring the mix to a workable slump with the rest.
For small pours, bagged premix saves buying and storing three separate materials. The cost block above compares both routes, and a concrete bag calculator counts the premix bags for any shape. Past roughly a cubic yard, ready-mix wins on time and consistency. If a supplier quotes aggregate by the tonne or you need to switch between yards, metres, pounds and kilograms, a unit converter settles it.
How to use this calculator
- 01Choose imperial or metric, then pick a mix ratio, a strength grade, or type your own parts.
- 02Enter the volume of concrete you need, or open the dimensions panel to work it out from a slab.
- 03Leave the water-cement ratio at its default, or drag it to see how strength changes.
- 04Read the bag count, sand, aggregate and water, then check the cost against premix.
- 05Pick your mixer size to turn the totals into a bucket recipe for one batch.
Common questions
What is the best concrete mix ratio?
What does a 1:2:4 concrete mix mean?
How many bags of cement are in a cubic yard of concrete?
How much cement is in a cubic metre of concrete?
What water-cement ratio should I use?
What is the mix ratio for M20 concrete?
What is the difference between M20 and C20 concrete?
Why do I need 1.54 times the volume in dry materials?
Is it cheaper to mix concrete from cement, sand and gravel than to use premix?
Can I use a table mix ratio for structural concrete?
- Concrete Calculator
- Concrete Bag Calculator for premix instead of batching
- Concrete Weight Calculator
- Concrete Slab Cost Calculator
- Unit Converter for yd³, m³, lb and kg
- Sand Calculator — coming soon
- Gravel Calculator — coming soon
Quantities use nominal volume ratios, a 1.54 dry-volume factor, and typical bulk densities (cement 94 lb/ft³, sand 100, aggregate 95). Real values vary with moisture, grading and bulking of sand. Strength estimates are indicative only and never replace trial mixes, cube tests or the advice of a structural engineer. Prices are editable placeholders. Last updated: October 1, 2026.